codeghi codeghi is offline URGENT PLEASE:  Project Calendar company holidays Windows 7 64bit URGENT PLEASE:  Project Calendar company holidays Office 2010 64bit
Advanced Beginner
 
Join Date: Jan 2010
Posts: 38
codeghi is on a distinguished road
Default

Hello Barry,
if you manage the subprojects via a Master project file, you should have a resource project pool.
You must open the resource project not in "read only option" but in "read-write option", so you can make changes to resource information.
After opening the resource project, click in "project" tab and then in "change working time": now you can planning the company Holiday setting the non-workings days in the base calendar.
Ensure to save the file when you close it: when you'll open a subproject file, you should view the changes.
Regards
Codeghi
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
URGENT PLEASE:  Project Calendar company holidays Need some urgent condensed Project knowledge!! Halesowenmum Project 1 10-06-2014 06:18 PM
Setting Emails to be send in calendar holidays to group of people Afshin r Outlook 0 11-13-2012 05:19 PM
URGENT PLEASE:  Project Calendar company holidays New calendar in Outlook, no holidays Dirtnapepr Outlook 2 09-15-2010 06:07 AM
outlook 2007 holidays won't load to calendar rec Outlook 0 07-08-2010 12:52 PM
Notification Mail In project server - Plz help urgent myanilkumar Project 0 01-19-2006 05:44 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:20 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft