Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 08-17-2016, 05:30 AM
JPolise JPolise is offline Critical path not displayed on Gantt Chart Windows 7 32bit Critical path not displayed on Gantt Chart Office 2010 32bit
Novice
Critical path not displayed on Gantt Chart
 
Join Date: Aug 2016
Posts: 6
JPolise is on a distinguished road
Default Critical path not displayed on Gantt Chart

I recently developed a project that initially showed the critical path in red. After some changes and updates, the critical path no longer shows on the Gantt Chart. I believe I have checked the appropriate boxes but nothing seems to work.



I'm using MSProject 2010. Can someone advise what could be happening or what I'm doing wrong?

Thanks.
Reply With Quote
  #2  
Old 08-21-2016, 05:43 AM
JulieS JulieS is offline Critical path not displayed on Gantt Chart Windows 7 64bit Critical path not displayed on Gantt Chart Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Try applying the Tracking Gantt view - does it appear? If filter for critical - do any tasks appear? Have you set a constraint on tasks such as Finish no Later than?
Reply With Quote
  #3  
Old 08-25-2016, 06:53 AM
JPolise JPolise is offline Critical path not displayed on Gantt Chart Windows 7 32bit Critical path not displayed on Gantt Chart Office 2010 32bit
Novice
Critical path not displayed on Gantt Chart
 
Join Date: Aug 2016
Posts: 6
JPolise is on a distinguished road
Default

In Tracking Gantt view the tasks all appear. When the filter for critical is applied it does generate a list of tasks. I do not believe I have set any constraints on any tasks although I can go back and verify. There are over 200 lines but maybe do a spot check.
Reply With Quote
  #4  
Old 08-25-2016, 07:21 AM
JulieS JulieS is offline Critical path not displayed on Gantt Chart Windows 7 64bit Critical path not displayed on Gantt Chart Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Take a look at the Gantt Chart Tool format ribbon. Did you inadvertently uncheck the box for Critical tasks?
Reply With Quote
  #5  
Old 08-25-2016, 07:25 AM
JPolise JPolise is offline Critical path not displayed on Gantt Chart Windows 7 32bit Critical path not displayed on Gantt Chart Office 2010 32bit
Novice
Critical path not displayed on Gantt Chart
 
Join Date: Aug 2016
Posts: 6
JPolise is on a distinguished road
Default

No, the Critical Tasks box (under Format) is checked.
Reply With Quote
  #6  
Old 08-25-2016, 07:37 AM
JPolise JPolise is offline Critical path not displayed on Gantt Chart Windows 7 32bit Critical path not displayed on Gantt Chart Office 2010 32bit
Novice
Critical path not displayed on Gantt Chart
 
Join Date: Aug 2016
Posts: 6
JPolise is on a distinguished road
Default

Julie, I noticed some tasks under the 'Advanced' tab under Information show 'As Soon as Possible' for the constraint type while in other tasks the field is not enabled. Could this be an issue?
Reply With Quote
  #7  
Old 08-25-2016, 08:59 AM
JulieS JulieS is offline Critical path not displayed on Gantt Chart Windows 7 64bit Critical path not displayed on Gantt Chart Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Have you customized the view with formatting? You may have luck re-setting the view to default - but you will lose any customization. Display a view other than the Gantt chart (assuming that is the one that is not showing correct information). Click the Task Ribbon and click on the drop down underneath the Gantt Chart button (far left). Choose Reset to Default.

Regarding the Constraint type - are you using Manually scheduled tasks? You cannot change the constraint type for manually scheduled tasks.
Reply With Quote
  #8  
Old 08-26-2016, 06:05 AM
JPolise JPolise is offline Critical path not displayed on Gantt Chart Windows 7 32bit Critical path not displayed on Gantt Chart Office 2010 32bit
Novice
Critical path not displayed on Gantt Chart
 
Join Date: Aug 2016
Posts: 6
JPolise is on a distinguished road
Default

I did the Reset to Default which produced no change. When I filter the critical tasks it doesn't list tasks that I know should be critical. This is very frustrating..

Your second comment answered my question concerning constraints. Thank you.
Reply With Quote
  #9  
Old 08-26-2016, 07:16 AM
JulieS JulieS is offline Critical path not displayed on Gantt Chart Windows 7 64bit Critical path not displayed on Gantt Chart Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Just to back up a second. Whether a task is critical or not is a mathematical calculation in Project. if a task has Total Slack >0, it is not critical. (Total slack in Project is = float in the PMI terminology world). If you add the Total Slack field to a table, do you see a value greater than zero? If so, by Project's definition it is not critical - while it may be very important to you.

You can alter the definition of critical in File > Options, Advanced and you can increase the value above zero.
Reply With Quote
  #10  
Old 08-26-2016, 08:10 AM
JPolise JPolise is offline Critical path not displayed on Gantt Chart Windows 7 32bit Critical path not displayed on Gantt Chart Office 2010 32bit
Novice
Critical path not displayed on Gantt Chart
 
Join Date: Aug 2016
Posts: 6
JPolise is on a distinguished road
Default

I believe we've found the issue. I increased the value above zero and the critical tasks now highlight in red. This appears to have solved a very annoying problem and I am very grateful for your help.

Thank you.
Reply With Quote
  #11  
Old 08-26-2016, 08:28 AM
JulieS JulieS is offline Critical path not displayed on Gantt Chart Windows 7 64bit Critical path not displayed on Gantt Chart Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome.
Reply With Quote
  #12  
Old 05-17-2021, 06:56 PM
Ry Pe Ry Pe is offline Critical path not displayed on Gantt Chart Windows 10 Critical path not displayed on Gantt Chart Office 2016
Novice
 
Join Date: May 2021
Posts: 1
Ry Pe is on a distinguished road
Default My Solution

My Solution:

After showing slack (format-slack tickbox) on my Gant the line showed my finish date like 4 months after my actual finish which nerfed my critical path.

File -
options -
advanced -
Calculation options for this project -
move end of completed parts after status date back to status date.

This reset the slack back and allowed my CP to work again.

Found this thread which led me to my solution so thought I'd create a login and post. Hope this helps others.

-Ryan
Reply With Quote
  #13  
Old 05-19-2021, 11:50 AM
miless2111s miless2111s is offline Critical path not displayed on Gantt Chart Windows 7 32bit Critical path not displayed on Gantt Chart Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

Quote:
Originally Posted by JPolise View Post
I believe we've found the issue. I increased the value above zero and the critical tasks now highlight in red. This appears to have solved a very annoying problem and I am very grateful for your help.

Thank you.
One thing that I have found with MSP is that I always have a dummy milestone at the end of the plan which is called "fake CPA" and is a long way in the future. Then I use deadlines to investigate the critical path to any given location in the plan by copying the finish date into the deadline field. I did a blog post on this which might be interesting?
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Critical Path workload forecasts Planner18 Project 1 07-01-2015 01:34 PM
Resource List displayed in Gantt Chart - Anyway to wrap text? wildzero Project 3 05-29-2014 05:46 AM
Critical Path Length ketanco Project 5 03-15-2013 01:12 PM
critical path starting in future ketanco Project 5 07-27-2012 02:50 PM
Critical path not displayed on Gantt Chart Critical Path w/ 2 Calendars AndreT Project 6 07-27-2011 11:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:05 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft