#1
|
|||
|
|||
Adding task costs
It seems that some of the Cost columns add up the costs in the headers but others dont.
"Cost" does but "Baseline Cost" doesn't. What is the reason for that? /Møller |
#2
|
|||
|
|||
When did you save the baseline? Before you added all tasks? Did you save a baseline only for selected tasks and not chose to roll the up? Have you tried saving a new baseline? Did you actually save the baseline or just type in the dates? I don't see a save date on the baseline.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Costs A B C D | cajos | Project | 1 | 03-24-2016 06:26 AM |
Materials/Work Costs Per task | cool28uo | Project | 1 | 02-01-2015 03:59 PM |
Copy and Paste of a Task...Including all of the Task's 'children'...to a new task | KRTSTARRYNIGHT | Project | 1 | 07-01-2014 06:54 AM |
Costs are not adding to the summary task in cost1 column | ketanco | Project | 1 | 06-14-2012 03:23 PM |
Non-recurring costs (NRE) | Trigger | Project | 1 | 04-26-2012 03:41 PM |