Hi,
Is there any way to set up dependencies between projects without the processor task being shown on the gant chart?

e.g.
Project A is procurement with tasks showing arrival times for various items.



Project N is for commissioning of a specific section and installation can not commence until the equipment arrives
but there is no need to show (and print) the procurement task (just treat it as a hidden predecessor).

Thanks
Reply With Quote
  #2  
Old 07-24-2016, 06:37 AM
JulieS JulieS is offline Cross project hidden dependency Windows 7 64bit Cross project hidden dependency Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

In File> Options, Advanced remove the check from "Show external predecessors."
Reply With Quote
  #3  
Old 07-25-2016, 06:53 PM
Dactech Dactech is offline Cross project hidden dependency Windows 8 Cross project hidden dependency Office 2013
Novice
Cross project hidden dependency
 
Join Date: Jul 2016
Posts: 2
Dactech is on a distinguished road
Default Hidden Cross Dependency

Thanks Julie
Reply With Quote
  #4  
Old 07-26-2016, 10:13 AM
JulieS JulieS is offline Cross project hidden dependency Windows 7 64bit Cross project hidden dependency Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome.
Reply With Quote
Reply

Tags
dependencies

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Cross project hidden dependency Gantt chart - reverse tasks dependency dnantia Project 11 01-16-2016 07:31 PM
Checkboxes selection dependency deboer Word 0 05-25-2014 02:25 PM
Dependency mapping using custom field - formula help alexRP Project 3 03-24-2014 08:03 AM
Cross Project Dependencies OTPM Project 6 01-18-2014 07:52 AM
Cross project hidden dependency Microsoft Project Dependency table into an AOA Network Diagram? acarmich Project 1 04-22-2013 09:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:46 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft