#1
|
|||
|
|||
Cross project hidden dependency
Hi,
Is there any way to set up dependencies between projects without the processor task being shown on the gant chart? e.g. Project A is procurement with tasks showing arrival times for various items. Project N is for commissioning of a specific section and installation can not commence until the equipment arrives but there is no need to show (and print) the procurement task (just treat it as a hidden predecessor). Thanks |
#2
|
|||
|
|||
In File> Options, Advanced remove the check from "Show external predecessors."
|
#3
|
|||
|
|||
Hidden Cross Dependency
Thanks Julie
|
#4
|
|||
|
|||
You're welcome.
|
Tags |
dependencies |
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Gantt chart - reverse tasks dependency | dnantia | Project | 11 | 01-16-2016 07:31 PM |
Checkboxes selection dependency | deboer | Word | 0 | 05-25-2014 02:25 PM |
Dependency mapping using custom field - formula help | alexRP | Project | 3 | 03-24-2014 08:03 AM |
Cross Project Dependencies | OTPM | Project | 6 | 01-18-2014 07:52 AM |
Microsoft Project Dependency table into an AOA Network Diagram? | acarmich | Project | 1 | 04-22-2013 09:33 AM |