Hi,
Is there any way to set up dependencies between projects without the processor task being shown on the gant chart? e.g. Project A is procurement with tasks showing arrival times for various items. Project N is for commissioning of a specific section and installation can not commence until the equipment arrives but there is no need to show (and print) the procurement task (just treat it as a hidden predecessor). Thanks |
Tags |
dependencies |
|
![]() |
||||