Pretty basic question, but I can’t find the answer in MS Help… I have the estimated number of man days’ effort per resource per task and I want to capture this in the resource allocation, e.g. Person X has 10 days’ work to do on Task Y, which is spread over 5 weeks. The work may not be 2 days per week, I just want to track overall effort. MS Project only seems to allow me to enter a %age. If you put in holidays for example, it changes the %age, which I don’t want to do. Am I missing something? Thanks.
Reply With Quote
  #2  
Old 07-15-2016, 05:23 PM
JulieS JulieS is offline Assigning number of days Windows 7 64bit Assigning number of days Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Set the task as Fixed Duration and enter 5 weeks duration. Split the screen to show the task form. Under Resource Names, select the resource and enter to 400 hours of work. Project will calculate the Peak Units and spread the 400 hours of work out evenly over the 5 week duration.
Reply With Quote
  #3  
Old 07-15-2016, 11:32 PM
MarcF MarcF is offline Assigning number of days Windows 7 64bit Assigning number of days Office 2013
Novice
Assigning number of days
 
Join Date: Jul 2016
Posts: 2
MarcF is on a distinguished road
Default

Thanks for the tip, will give this a try.
Reply With Quote
  #4  
Old 07-16-2016, 10:44 AM
JulieS JulieS is offline Assigning number of days Windows 7 64bit Assigning number of days Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome. Post back if you have further questions.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Calculate number of days in a table from a specific date tstolbert Word 2 06-25-2016 02:30 PM
Assigning number of days How do I get auto-updated "number of days since specified date" on MS word? terry795 Word 16 01-07-2016 04:33 PM
I want to link appointments by a fixed number of days ctandcf1 Outlook 0 10-29-2014 06:56 PM
Maximum number of working days reached= warning color perZZon Excel Programming 1 05-09-2014 03:01 PM
Assigning number of days Converting serial number to years, months and days hannu Excel 6 02-14-2013 09:21 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:59 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft