Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 07-10-2016, 05:55 PM
lordtopcat lordtopcat is offline Tasks behind schedule Windows 7 64bit Tasks behind schedule Office 2016
Novice
Tasks behind schedule
 
Join Date: Jul 2016
Posts: 1
lordtopcat is on a distinguished road
Default Tasks behind schedule

Hi Guys,



Not sure why this is so hard, as I would have thought it would be a common report.

I want to see what tasks are behind schedule. In my mind, the filter would be as simple as tasks with a finish date of <= today and complete % < 100%. However, I can not find a way to filter on today's date?

Surely this would be something that's used frequently? Obviously not, otherwise it would be there.

Can anyone assist? I am using Project 2016, if that helps.

Cheers.
Reply With Quote
  #2  
Old 07-12-2016, 05:21 AM
cookieburk cookieburk is offline Tasks behind schedule Windows 8 Tasks behind schedule Office 2013
Novice
 
Join Date: May 2016
Posts: 4
cookieburk is on a distinguished road
Default Tasks Behind Schedule

MPUG has a formula that addresses Late Tasks.

http://46ev833n9u2l3zs8zp44sst3tpr.w...DF-Version.pdf
Reply With Quote
  #3  
Old 07-12-2016, 02:49 PM
JulieS JulieS is offline Tasks behind schedule Windows 7 64bit Tasks behind schedule Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The Project Overview report shows late tasks. The Late Tasks Report shows late tasks. The Slipping Tasks report shows tasks where the finish date is past the deadline date. There are also late Tasks Filters, Status fields you can add. Will any of those help?
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Outlook 365 My Tasks: Tasks vs. TodoList--Sort? markg2 Outlook 0 04-17-2016 03:21 AM
My schedule shows all tasks as critical no matter how much float they have lenmacf Project 5 05-05-2014 07:57 AM
Question about tasks on critical path in MS Project schedule (with a twist) SomewhereinTX Project 7 01-06-2014 03:07 PM
updating not completed tasks or 0% tasks ketanco Project 3 08-24-2012 05:59 AM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:13 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft