  #1  
Old 07-10-2016, 03:05 PM
Guloluseus Guloluseus is offline Viewing "paste link" data Windows 7 64bit Viewing "paste link" data Office 2010 32bit
Competent Performer
Viewing "paste link" data
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default Viewing "paste link" data

I have a number of tasks in a programme which represent the time specific members of staff are required on site. These have been placed in as hammock tasks. this was supposed to be a final edit, but a number of items have changed, been added or removed and consequently I have no idea what the original links where.

Is it possible to see what task the link was taken from?

thanks
Reply With Quote
  #2  
Old 07-12-2016, 02:52 PM
JulieS JulieS is offline Viewing "paste link" data Windows 7 64bit Viewing "paste link" data Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you double click on the linked field (Start date for example) it will select the field where the linked data comes from.
Reply With Quote
  #3  
Old 07-12-2016, 03:06 PM
Guloluseus Guloluseus is offline Viewing "paste link" data Windows 7 64bit Viewing "paste link" data Office 2010 32bit
Competent Performer
Viewing "paste link" data
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

Thanks for the reply, I think I may have mis stated what I did
The linked info is the start and finish date- so for task "X", I copied the start date of task a and pasted into task x start, then copied task b finish date and pasted into task x finish. Not an ideal solution, but it performed the function that was required- or at least, the one I was told was required!

I resorted to using a summary task with start dates for each resource as a direct ss link, and the same for finish, then hammocked these to give durations. That way at least I know where the info came from.

Reply With Quote
  #4  
Old 07-12-2016, 03:45 PM
JulieS JulieS is offline Viewing "paste link" data Windows 7 64bit Viewing "paste link" data Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

No - I understand that you have created a hammock task using paste link? The method I noted should work if you used paste link.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
How to "hard link" two adjacent cells to a data validation drop down list? Geza59 Excel 10 10-19-2012 11:56 AM
Viewing "paste link" data Paste data in "Accounting"format from Excel into Word changes formatting cory_0101 Word 4 10-17-2012 12:30 PM
Viewing "paste link" data How to choose a "List" for certain "Heading" from "Modify" tool? Jamal NUMAN Word 2 07-03-2011 03:11 AM
Viewing "paste link" data How can I paste cell "A1" contents to cell "B1" if cell "A1" is not blank? Learner7 Excel 1 04-25-2011 04:39 AM
Viewing "paste link" data How to use "if" to copy and paste data tareq Excel Programming 13 01-26-2011 03:34 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:57 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft