Old 07-07-2016, 08:16 AM
zamshabeer zamshabeer is offline Set start and end dates of one task based on one other task only Windows 8 Set start and end dates of one task based on one other task only Office 2013
Novice
Set start and end dates of one task based on one other task only
 
Join Date: Jul 2016
Posts: 1
zamshabeer is on a distinguished road
Default Set start and end dates of one task based on one other task only

I am trying to set the start date and the finish date of a task based on one other task alone.

In other words:

I have task A and task B

Task A starts on 1-Jan-16 and ends on 10-Jan-16

I want task B to start on the same day that task A starts (i.e on 1-Jan) and I want task B to end on the same day that task A ends (i.e on 10-Jan). But I don't want to enter details for task B manually. When I change the start date or duration for task A, I want the details of task B to update automatically.

I tried doing this by setting the predecessor for task B as aSS,aFF. But Project wouldn't let me do this.

Is there a way to address my issue?

Thanks in advance


Best regards
Zam
Reply With Quote
  #2  
Old 07-07-2016, 11:25 AM
JulieS JulieS is offline Set start and end dates of one task based on one other task only Windows 7 64bit Set start and end dates of one task based on one other task only Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You are looking for a hammock task.

See https://support.microsoft.com/en-us/kb/141733
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Set start and end dates of one task based on one other task only force task start on monday pascalbidouille Project 2 07-01-2015 01:57 PM
Set start and end dates of one task based on one other task only Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
Set start and end dates of one task based on one other task only Excel to auto populate dates based on start and end patidallas22 Excel Programming 9 04-21-2014 03:14 PM
How to get project to automatically pull in task dates? Moe Szylak Project 2 04-26-2012 12:37 PM
Set start and end dates of one task based on one other task only Task Start and End Dates OTPM Project 2 12-04-2011 09:14 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:59 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft