Old 07-04-2016, 05:18 AM
jasond77 jasond77 is offline MS Project levelling - how to stop longest task scheduled first Windows 8 MS Project levelling - how to stop longest task scheduled first Office 2010 32bit
Novice
MS Project levelling - how to stop longest task scheduled first
 
Join Date: Jul 2016
Posts: 2
jasond77 is on a distinguished road
Default MS Project levelling - how to stop longest task scheduled first

Hi All, new member to the forum, so thanks in advance for reading my query

I have noticed if you change a batch of tasks to update the resource, then level those tasks, MSP schedules the longest task first.



I list my tasks in chronological order so I'd like levelling to consider this when assigning tasks to the same resources

Once I level some tasks I'd also like that to be 'locked down' and if I assign tasks to someone further down the plan I'd like levelling to ignore the batch above (I understand I can use dependencies for this, but that's a hack)
Reply With Quote
  #2  
Old 07-04-2016, 05:27 AM
jasond77 jasond77 is offline MS Project levelling - how to stop longest task scheduled first Windows 8 MS Project levelling - how to stop longest task scheduled first Office 2010 32bit
Novice
MS Project levelling - how to stop longest task scheduled first
 
Join Date: Jul 2016
Posts: 2
jasond77 is on a distinguished road
Default

Quote:
Originally Posted by jasond77 View Post
Hi All, new member to the forum, so thanks in advance for reading my query

I have noticed if you change a batch of tasks to update the resource, then level those tasks, MSP schedules the longest task first.

I list my tasks in chronological order so I'd like levelling to consider this when assigning tasks to the same resources

Once I level some tasks I'd also like that to be 'locked down' and if I assign tasks to someone further down the plan I'd like levelling to ignore the batch above (I understand I can use dependencies for this, but that's a hack)
Sorry, I should have searched first. Thanks to https://www.msofficeforums.com/proje...ask-first.html I have the answer

Great forum, thanks
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Auto scheduling issue - longest task first? Project_64 Project 3 01-25-2016 01:14 PM
MS Project levelling - how to stop longest task scheduled first MS Project Resource Capacity and Auto-levelling Senor_Babs Project 2 11-01-2014 02:46 PM
MS Project levelling - how to stop longest task scheduled first Levelling resource's units to calculate duration task codeghi Project 10 03-01-2014 08:13 AM
MS Project levelling - how to stop longest task scheduled first Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
MS Project levelling - how to stop longest task scheduled first MS Project - Maximizing resource levelling aguatorito Project 3 03-10-2013 06:08 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:27 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft