Hi all,
When updating a task using Mark on Track, sometimes a project will update completion to the end of the previous day, but other times it will update to the end of the current day. Obviously this is affecting outstanding work content when leveling resource. I’m sure there must be a simple setting somewhere to determine this, but I have not been able to find it. I always have my project Status Date set as NA. Any help will be greatly appreciated. I am using 2013 if that makes any difference to the solution. Paul |
#2
|
|||
|
|||
![]()
The "Mark on Track" command works with the status date. Is there a reason why you aren't setting the status date?
What times were the tasks scheduled to end? |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Outlook Tasks 'current view'? | markg2 | Outlook | 0 | 07-27-2014 08:10 AM |
Need To Compare Two Worksheets, Update Current Records And Insert New | David92595 | Excel | 1 | 07-20-2012 07:00 AM |
Export Excel tasks into Outlook Tasks (2007 Version on both) | crazedmom | Excel | 0 | 12-29-2011 07:55 AM |
![]() |
KIM SOLIS | Excel | 2 | 11-04-2011 06:09 PM |
![]() |
Styler001 | Word | 4 | 01-25-2010 06:40 PM |