ksa5024 ksa5024 is offline Displaying Code in a task usage view Windows 7 64bit Displaying Code in a task usage view Office 2013
Novice
Displaying Code in a task usage view
 
Join Date: Jun 2016
Posts: 1
ksa5024 is on a distinguished road
Default Displaying Code in a task usage view

I am using Microsoft Project 2013. I have built my resources to include the "Code" for their department. When I view the Task Usage view I am unable to add the "Code" column to the view so that I can see (and filter on) the department. The Code field is not even available to select.



I am trying to run a view and/or report that will display (by task) the ID I have assigned to the task, the cost of the task, the resource name and their Code. How can I best do this? I have tried multiple views and cost reports but none seem to have available all the columns I need.
Reply With Quote
  #2  
Old 06-15-2016, 06:15 PM
JulieS JulieS is offline Displaying Code in a task usage view Windows 7 64bit Displaying Code in a task usage view Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

There are very few fields that show in both a resource view and a task view. You could use the Initial field and then add the Resource Initials field to the Task Usage view. As long as you as not using the Japanese version of Project, you can also add the Phonetics field to the resource sheet - and then add Resource Phonetics to the Task Usage view. It will carry the phonetics data back to the task row.

See: http://social.technet.microsoft.com/...ssignment.aspx for a full discussion and

http://social.technet.microsoft.com/...-in-views.aspx
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Displaying Code in a task usage view Resource Usage View bumpui Project 7 06-18-2014 05:32 AM
Displaying Code in a task usage view Inactive tasks and resource usage view codeghi Project 1 05-05-2014 06:59 AM
How to Display Summary Values using Group filter in Task Usage Glenn Faulkner Project 5 03-31-2014 01:14 PM
Finish Variance in Resouce Usage View stct Project 3 05-17-2011 02:07 PM
Accessing Assignment Detail Data in Task Usage View CGM3 Project 0 10-05-2010 05:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:22 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft