I am using Microsoft Project 2013. I have built my resources to include the "Code" for their department. When I view the Task Usage view I am unable to add the "Code" column to the view so that I can see (and filter on) the department. The Code field is not even available to select.
I am trying to run a view and/or report that will display (by task) the ID I have assigned to the task, the cost of the task, the resource name and their Code. How can I best do this? I have tried multiple views and cost reports but none seem to have available all the columns I need. |
#2
|
|||
|
|||
There are very few fields that show in both a resource view and a task view. You could use the Initial field and then add the Resource Initials field to the Task Usage view. As long as you as not using the Japanese version of Project, you can also add the Phonetics field to the resource sheet - and then add Resource Phonetics to the Task Usage view. It will carry the phonetics data back to the task row.
See: http://social.technet.microsoft.com/...ssignment.aspx for a full discussion and http://social.technet.microsoft.com/...-in-views.aspx |
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Resource Usage View | bumpui | Project | 7 | 06-18-2014 05:32 AM |
Inactive tasks and resource usage view | codeghi | Project | 1 | 05-05-2014 06:59 AM |
How to Display Summary Values using Group filter in Task Usage | Glenn Faulkner | Project | 5 | 03-31-2014 01:14 PM |
Finish Variance in Resouce Usage View | stct | Project | 3 | 05-17-2011 02:07 PM |
Accessing Assignment Detail Data in Task Usage View | CGM3 | Project | 0 | 10-05-2010 05:56 AM |