  #1  
Old 06-02-2016, 02:44 PM
walkinghere walkinghere is offline How to set the start point for ordinal labels in timescale Windows 10 How to set the start point for ordinal labels in timescale Office 2013
Novice
How to set the start point for ordinal labels in timescale
 
Join Date: Jun 2016
Posts: 2
walkinghere is on a distinguished road
Default How to set the start point for ordinal labels in timescale

In Project 2013, how do you set the start date for the ordinal labels when you want them to start after the first activity? In previous versions of Project I used to change the Project Start Date and constrain the earlier tasks, but that doesn't work in version 2013.
Reply With Quote
  #2  
Old 06-02-2016, 02:47 PM
JulieS JulieS is offline How to set the start point for ordinal labels in timescale Windows 7 64bit How to set the start point for ordinal labels in timescale Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm afraid I don't know what you mean. You still set the start date of the Project in Project Information. Create the links to the first activity.
Reply With Quote
  #3  
Old 06-02-2016, 04:32 PM
walkinghere walkinghere is offline How to set the start point for ordinal labels in timescale Windows 10 How to set the start point for ordinal labels in timescale Office 2013
Novice
How to set the start point for ordinal labels in timescale
 
Join Date: Jun 2016
Posts: 2
walkinghere is on a distinguished road
Default

Hi, see the attachment for a specific example. I am trying to make it such that the W1, W2 count starts on the 20/06/16 because that's when the contract period starts. In the live screen the W1 starts at 06/06/16, even though I have set the Project Start date at 20/06/16 - see Figure 1.
Since the first forum mail, I have found that the W1, W2 moves to where I want it (20/06/16) in the Print Preview screen, as per Figure 2. This gives me my solution. Ideally the live screen would match the print preview screen, but I'm not going to quibble.
Attached Files
File Type: pdf MSP eg.pdf (119.1 KB, 11 views)
Reply With Quote
  #4  
Old 06-05-2016, 10:12 AM
JulieS JulieS is offline How to set the start point for ordinal labels in timescale Windows 7 64bit How to set the start point for ordinal labels in timescale Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Reading between the lines. You need tasks to appear in the Gantt chart before the start date of the project. You'd like those tasks to appear as -W1, -W2 on the Gantt chart.
I just tested with Project 2013 Pro 15.0.4823.1000 and they appear as you need in both Print Preview and on screen. What release of Project are you working with? An update may be in order:

https://blogs.technet.microsoft.com/...pport/p/msp13/
Reply With Quote
Reply

Tags
ordinals, project start date

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to set the start point for ordinal labels in timescale Power Point 2016 keeps crashing and won't start normally Aymincendiary PowerPoint 1 01-30-2016 05:44 PM
Formatting th at the end of ordinal dates DBlomgren Publisher 0 01-23-2016 09:44 AM
How to set the start point for ordinal labels in timescale Costs are shifted when changing the timescale Mareike_# Project 5 12-01-2014 07:18 AM
MS Project-timescale in hours John Franklin Project 5 10-30-2013 08:41 AM
MergeField Alphabetic Ordinal substitutes _ for Z khinnenkamp Mail Merge 1 09-29-2013 07:01 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:18 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft