#1
|
|||
|
|||
Problem with non-working days in MP2013
Hello,
I have a project planning based on a resource pool. I assign the non-working days in the calendar of resources on the "Resource.mpp" file. After this modification, I see a correct planning adjusting in MP2010 that takes into account of non-working days, while with MP2013 I don't see it! I have attached a file wherewith you could verified it: if I assign non working days for "Luke" resource (13-16 June), the "congress" task in "Task1" file is not re-allocated in MP2013. I ask you if there is a particular setting in MP2013 version that could resolve the problem. Bye |
#2
|
|||
|
|||
When I open Task1.mpp and choose "Open Resource Pool" I see the assignment for Luke starting on 6/10 and ending on 6/21 for the Congress task. He is not scheduled to work from June 13 - 16.
When you open Task1 are you opening the pool file? Tested using Project 2013 version: 15.0.4823.1000 |
#3
|
|||
|
|||
Hello Julies,
I discovered the problem. Open the "Master.mpp", click on "Resource Pool->Share Resources...": the default setting on conflict with calendar or resource information is "Sharer takes precedence". I had to click on "Pool takes precedence" to resolve the problem. Regards. Luca |
#4
|
|||
|
|||
I'm glad you were able to sort it out. Any sharing should always be set to "Pool takes precedence." To clarify however, the pool does not need to be attached to the master unless you have tasks that are only in the master file and are not contained in any inserted project file.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
reminder for every 15 working days | araamuthan | Outlook | 1 | 03-25-2015 11:49 PM |
reminder for every 15 working days | araamuthan | Excel | 0 | 03-25-2015 06:49 AM |
Maximum number of working days reached= warning color | perZZon | Excel Programming | 1 | 05-09-2014 03:01 PM |
Master Projects with different Working Days | Philip.Skeet | Project | 2 | 08-19-2011 09:45 AM |
Non-Working Days on Gantt | JayTT | Project | 1 | 01-28-2011 05:42 AM |