Problem with non-working days in MP2013
 
Join Date: Jan 2010
Posts: 38
codeghi is on a distinguished road
Default Problem with non-working days in MP2013

Hello,


I have a project planning based on a resource pool.
I assign the non-working days in the calendar of resources on the "Resource.mpp" file.
After this modification, I see a correct planning adjusting in MP2010 that takes into account of non-working days, while with MP2013 I don't see it!
I have attached a file wherewith you could verified it: if I assign non working days for "Luke" resource (13-16 June), the "congress" task in "Task1" file is not re-allocated in MP2013.
I ask you if there is a particular setting in MP2013 version that could resolve the problem.
Bye
Attached Files
File Type: zip planning_test.zip (99.0 KB, 8 views)
Reply With Quote
  #2  
Old 06-02-2016, 02:46 PM
JulieS JulieS is offline Problem with non-working days in MP2013 Windows 7 64bit Problem with non-working days in MP2013 Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

When I open Task1.mpp and choose "Open Resource Pool" I see the assignment for Luke starting on 6/10 and ending on 6/21 for the Congress task. He is not scheduled to work from June 13 - 16.

When you open Task1 are you opening the pool file? Tested using Project 2013 version: 15.0.4823.1000
Reply With Quote
  #3  
Old 06-11-2016, 11:46 PM
codeghi codeghi is offline Problem with non-working days in MP2013 Windows 7 64bit Problem with non-working days in MP2013 Office 2010 64bit
Advanced Beginner
Problem with non-working days in MP2013
 
Join Date: Jan 2010
Posts: 38
codeghi is on a distinguished road
Default

Hello Julies,
I discovered the problem.
Open the "Master.mpp", click on "Resource Pool->Share Resources...": the default setting on conflict with calendar or resource information is "Sharer takes precedence".
I had to click on "Pool takes precedence" to resolve the problem.
Regards.
Luca
Reply With Quote
  #4  
Old 06-12-2016, 12:00 PM
JulieS JulieS is offline Problem with non-working days in MP2013 Windows 7 64bit Problem with non-working days in MP2013 Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm glad you were able to sort it out. Any sharing should always be set to "Pool takes precedence." To clarify however, the pool does not need to be attached to the master unless you have tasks that are only in the master file and are not contained in any inserted project file.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Problem with non-working days in MP2013 reminder for every 15 working days araamuthan Outlook 1 03-25-2015 11:49 PM
reminder for every 15 working days araamuthan Excel 0 03-25-2015 06:49 AM
Maximum number of working days reached= warning color perZZon Excel Programming 1 05-09-2014 03:01 PM
Master Projects with different Working Days Philip.Skeet Project 2 08-19-2011 09:45 AM
Problem with non-working days in MP2013 Non-Working Days on Gantt JayTT Project 1 01-28-2011 05:42 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:16 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft