Flexible Working Hours
Hi! I have a resource that can only work 2 days a week, but they can be any days between Monday and Friday. Is there a way to express this rule in Project 2013? Thanks, Tom |
#2
|
|||
|
|||
Does the resource have to work two full 8 hours days or are you just saying that in a 40 hour time period, the resource can work 16 hours? If the resource can work full days only, then the best work around is to change his/her calendar to only work two specific days. If s/he can work a maximum of 16 hours in a week - you can set his/her max units to 40%. That will spread the 16 hours of work out over the week.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Actual working hours per day | climbatron | Project | 2 | 12-17-2015 03:13 PM |
How flexible is ExportFragment? | Hoxton118 | Word VBA | 2 | 06-17-2014 06:23 AM |
DateDiff gives error when working after 24 hours | TimTDP | Excel | 3 | 07-18-2012 12:50 AM |
calendar -reduced working hours | pm_newbie | Project | 7 | 01-17-2012 10:34 AM |
Date and time calcs excluding non-working hours | mrsatchmo | Excel | 1 | 01-26-2011 08:50 AM |