Default Project Late Status Changes from One User to Another

MS Project 2010 Pro Standalone. I have a project file that has three late tasks. Of the three tasks, one is 60% complete, a duration of 77 days, start date 3/21/16 and end date of 7/7/16. Status date is 5/24/16; calendar is US and Federal Holidays. When I send this project file to a colleague this task is shown as on schedule. We have verified the status date and calendar in my colleague's MS Project. Any ideas on why/how the late calculation is different?
Reply With Quote
  #2  
Old 05-31-2016, 10:19 AM
JulieS JulieS is offline Project Late Status Changes from One User to Another Windows 7 64bit Project Late Status Changes from One User to Another Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

To the best of my knowledge, Project does not perform a calculation when the file is opened. If he/she pressed F9 to force a calculation, do you see the status update?
Reply With Quote
  #3  
Old 05-31-2016, 11:12 AM
cookieburk cookieburk is offline Project Late Status Changes from One User to Another Windows 8 Project Late Status Changes from One User to Another Office 2013
Novice
Project Late Status Changes from One User to Another
 
Join Date: May 2016
Posts: 4
cookieburk is on a distinguished road
Default

Thanks for the reply Julie. No, the status does not change.
Reply With Quote
  #4  
Old 05-31-2016, 01:06 PM
cookieburk cookieburk is offline Project Late Status Changes from One User to Another Windows 8 Project Late Status Changes from One User to Another Office 2013
Novice
Project Late Status Changes from One User to Another
 
Join Date: May 2016
Posts: 4
cookieburk is on a distinguished road
Default Project file corrupted

As I am rebuilding the schedule in my original post, I find several sub projects are corrupted.

Thanks for your input.
Reply With Quote
  #5  
Old 06-01-2016, 12:31 PM
JulieS JulieS is offline Project Late Status Changes from One User to Another Windows 7 64bit Project Late Status Changes from One User to Another Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Ah, thanks for the update. Corrupted subprojects will most certainly cause tons of issues.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Project Late Status Changes from One User to Another Project Status and Late Tasks - Incorrect BarryB Project 4 08-02-2015 01:50 PM
Project Late Status Changes from One User to Another in project 2013 standard how to achieve multi-user editting? Lorrainewjh Project 5 07-01-2015 05:57 PM
RAG Status on Project 2013 deepsk Project 3 04-23-2015 07:26 AM
Can you review status in Project from a previous time prior to "Today" StevieMar Project 3 04-30-2014 09:42 AM
Project Late Status Changes from One User to Another MS Project Start Dates not matching the Status Date sjodom Project 3 12-04-2011 08:45 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:36 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft