#1
|
|||
|
|||
Project Late Status Changes from One User to Another
MS Project 2010 Pro Standalone. I have a project file that has three late tasks. Of the three tasks, one is 60% complete, a duration of 77 days, start date 3/21/16 and end date of 7/7/16. Status date is 5/24/16; calendar is US and Federal Holidays. When I send this project file to a colleague this task is shown as on schedule. We have verified the status date and calendar in my colleague's MS Project. Any ideas on why/how the late calculation is different? |
#2
|
|||
|
|||
To the best of my knowledge, Project does not perform a calculation when the file is opened. If he/she pressed F9 to force a calculation, do you see the status update?
|
#3
|
|||
|
|||
Thanks for the reply Julie. No, the status does not change.
|
#4
|
|||
|
|||
Project file corrupted
As I am rebuilding the schedule in my original post, I find several sub projects are corrupted.
Thanks for your input. |
#5
|
|||
|
|||
Ah, thanks for the update. Corrupted subprojects will most certainly cause tons of issues.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Project Status and Late Tasks - Incorrect | BarryB | Project | 4 | 08-02-2015 01:50 PM |
in project 2013 standard how to achieve multi-user editting? | Lorrainewjh | Project | 5 | 07-01-2015 05:57 PM |
RAG Status on Project 2013 | deepsk | Project | 3 | 04-23-2015 07:26 AM |
Can you review status in Project from a previous time prior to "Today" | StevieMar | Project | 3 | 04-30-2014 09:42 AM |
MS Project Start Dates not matching the Status Date | sjodom | Project | 3 | 12-04-2011 08:45 AM |