Total Slack Calculation Incorrect in SubProjects vs MasterPlan
Hi All,
I have created a Master Plan with multiple sub projects, using Microsoft Project Pro 2010. My Critical Path has negative slack, which is properly displayed on the Master-plan, however when I open a subproject, that is in the Critical Path with negative slack, the Total slack shows zero days instead of (-)xx days. Example: In the Master Plan, The last task on Project A is a milestone, that is linked to the first task on Project B. In the Master Plan, Project A has (-16) days of Total slack and Project B has (-16) days of Total slack. When I open Project A - Total slack is zero When I open Project B - Total slack is (-16) days I have run some tests but none seem to solve the issue: 1.I have selected and deselected Multi Critical Path box - Still show the same issue 2.I have selected and deselected the "Inserted Projects are Calculated Like Summary Tasks" - Still show the same issue 3.The calendar is the same across all the sub-projects and Master-plan. 4.The Custom Fields are the same across all the sub-projects and Master-plan. 5. I have Service Pack 2 on my PC Has anyone came across with this issue? Thank you for your help in advance |
#2
|
|||
|
|||
Do you have any tasks in the master project that are not part of the subproject? Normally negative total slack is from a missed deadline or constraint. Have you added constraints in the master project that are not in the subprojects?
|
#3
|
|||
|
|||
Hi Julie,
thank you for your reply. I have a constraint in Sub - Project B, however I don't see why the negative slack wouldn't appear in project A anyway, since the activities in this file are preceding Project B. |
#4
|
|||
|
|||
Are you opening subproject A outside of the master project? If so, it is not calculating the negative slack due to its relationship to project B.
|
Tags |
masterplan, subprojects, total slack |
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Very complicated calculation of total hours worked (PLEASE HELP) | APreston | Excel | 1 | 05-08-2016 02:58 AM |
Total Slack and Activity with SS Successor only | ketanco | Project | 3 | 05-14-2014 01:59 PM |
total slack of activities and schedule logic | ketanco | Project | 1 | 08-04-2012 05:58 AM |
total slack not changing when changing duration | ketanco | Project | 1 | 02-11-2012 07:23 AM |
Total Slack not updating | damianb | Project | 0 | 06-25-2010 11:48 AM |