  #3  
Old 05-31-2016, 04:01 AM
ana ana is offline Total Slack Calculation Incorrect in SubProjects vs MasterPlan Windows 7 32bit Total Slack Calculation Incorrect in SubProjects vs MasterPlan Office 2010 32bit
Novice
Total Slack Calculation Incorrect in SubProjects vs MasterPlan
 
Join Date: May 2016
Posts: 2
ana is on a distinguished road
Default

Hi Julie,

thank you for your reply.

I have a constraint in Sub - Project B, however I don't see why the negative slack wouldn't appear in project A anyway, since the activities in this file are preceding Project B.
Reply With Quote
 

Tags
masterplan, subprojects, total slack



Similar Threads
Thread Thread Starter Forum Replies Last Post
Total Slack Calculation Incorrect in SubProjects vs MasterPlan Very complicated calculation of total hours worked (PLEASE HELP) APreston Excel 1 05-08-2016 02:58 AM
Total Slack and Activity with SS Successor only ketanco Project 3 05-14-2014 01:59 PM
total slack of activities and schedule logic ketanco Project 1 08-04-2012 05:58 AM
Total Slack Calculation Incorrect in SubProjects vs MasterPlan total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
Total Slack not updating damianb Project 0 06-25-2010 11:48 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:24 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft