Default Custom Duration Formula

I'm working with mostly all custom fields in my project, such as manually entered Start dates and Finish dates. I'm not sure why I cant use a "duration1" custom formula to calculate my projected and actual duration.



My formula looks like this [Start4]-[Start3]

Start4 is my "projected start"
Start3 is my "projected finish"

I even tried doing it as ([Start4]-[Start3])/480 so it used minutes per day, but that didn't work either.

please help.
thanks.
Reply With Quote
  #2  
Old 05-11-2016, 05:11 AM
JulieS JulieS is offline Custom Duration Formula Windows 7 64bit Custom Duration Formula Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Try:
ProjDateDiff([Start4],[Start3],"standard")

Assuming you are using the Standdard calendar as the Project calendar. If not, substitute your calendar name.
Reply With Quote
  #3  
Old 05-17-2016, 02:04 AM
miless2111s miless2111s is offline Custom Duration Formula Windows 7 32bit Custom Duration Formula Office 2007
Advanced Beginner
 
Join Date: May 2016
Posts: 32
miless2111s is on a distinguished road
Default

For clarity what not use finish3 rather than start4? That way your plan will be easier to understand when you come back to it another time?
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Custom Duration Formula Custom Formula help jkdiesel Project 13 05-20-2016 08:08 AM
Custom Duration Formula Custom fields formula fragono Project 2 03-02-2016 11:03 AM
Custom Duration Formula Task Name / date in a formula or custom column ebilbrough Project 6 11-05-2015 12:59 PM
Dependency mapping using custom field - formula help alexRP Project 3 03-24-2014 08:03 AM
custom formula for duration ericfons Project 0 03-23-2010 01:18 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:43 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft