Are Projected Costs and Actual Costs more custom fields? If so, you need to set the summary tasks to roll up. In the customize field dialog, select to either sum, min or max. But I have to ask - why all the custom calculations? If you save a baseline you'll have "projected costs" in baseline cost. If you apply tracking - you'll have actual costs.
|
|
![]() |
||||