  #3  
Old 05-11-2016, 06:36 AM
jkdiesel jkdiesel is offline Custom Formula help Windows 7 64bit Custom Formula help Office 2013
Novice
Custom Formula help
 
Join Date: May 2016
Posts: 11
jkdiesel is on a distinguished road
Default Scheduling

Thanks Julie. My next issue is this: why does MS project automatically put Start dates in for summary tasks? I want to have manually scheduled dates for all my date fields - and I cant get my Projected Cost and Actual Cost to rollup all the way? If you look at the photo I attached, you'll see that my projected duration and actual duration, projected cost and actual cost formulas are finally right for the 5th line down (its a subtask), and I have those columns set to rollup using the sum. it appears that the actual cost column rolled up a little bit but not all the way to the top summary task.

Thanks for the help.
Attached Images
File Type: png Untitled.png (256.9 KB, 30 views)
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Custom Formula help Custom fields formula fragono Project 2 03-02-2016 11:03 AM
Custom Formula help Task Name / date in a formula or custom column ebilbrough Project 6 11-05-2015 12:59 PM
Dependency mapping using custom field - formula help alexRP Project 3 03-24-2014 08:03 AM
Custom Formula help Delay prediction formula for custom fields Imagios Project 5 04-25-2012 06:32 AM
custom formula for duration ericfons Project 0 03-23-2010 01:18 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:03 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft