JulieS JulieS is offline Resource Overallation not flagged correctly Windows 7 64bit Resource Overallation not flagged correctly Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What are your leveling settings? Day by Day? Week by week? Even though the task are overlapping are the assignments? Look at the Resource Usage view and add Start and Finish fields to the table (left side). If the tasks are fixed duration with resources with differing amounts of work - the assignments may not overlap - therefore - no overallocation.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource Overallation not flagged correctly Resource Usage View - Is it possible to display resource names Andrea Schanz Project 6 09-22-2014 07:47 AM
Resource Overallation not flagged correctly Resource assignment with resource calendars joday48 Project 6 08-19-2014 05:49 AM
Resource Assignment Summary Line Not Adding Up Correctly PeteS Project 2 07-18-2014 06:24 AM
Resource Usage view does not correctly export to a Visual Report cergon Project 3 04-25-2014 06:10 AM
Filter flagged within 24hrs of received AmbiguousLime Outlook 0 07-23-2013 11:50 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:43 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft