Under utilization of resources
Why is there no work on Task B during the time Task A is being carried out? There is a worker available.
/Møller |
#2
|
|||
|
|||
How many Worker resources do you have? Resource Leveling in Project will never change assignment units. If you have 200% of workers and you have 200% assigned to Task B - Project will not drop assignment units to 100% during the time of Task A then increase it to 200% later on. You can manually contour resource assignments but Resource Leveling will not.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Resources - only allow users to select from resources pool | grazi | Project | 1 | 04-04-2014 11:12 AM |
Better way to views resources? | ctobola | Outlook | 1 | 03-20-2014 08:01 AM |
Multiple resources | Tedzer | Project | 1 | 11-12-2013 08:02 AM |
How to set task to be done by 4 resources each one after another? | lukusm | Project | 1 | 01-16-2012 07:21 AM |
Assigning resources. | Sergey M | Project | 0 | 01-25-2006 09:33 AM |