Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 04-12-2016, 06:53 AM
c991257 c991257 is offline Need help understanding critical path and feedback on programme. Windows 10 Need help understanding critical path and feedback on programme. Office 2016
Advanced Beginner
Need help understanding critical path and feedback on programme.
 
Join Date: Mar 2014
Location: Zambia
Posts: 61
c991257 is on a distinguished road
Default Need help understanding critical path and feedback on programme.

Hi.

I've made a programme for a one of our projects and have changed the traditional way that the programme is made.

We build roads and tend to use links to control the order in which the roads are built, however that never works well. I've changed that by not linking individual roads and used priorities and resources to control the order in which each road is built. I think that makes much more sense, however the consequence seems to be that the critical path is now decided by a single road (that last one), and if I set MS Project to calculate multiple critical then almost everything becomes critical.

I would like opinions on whether or not the way I've done the programme is "correct" but also comments on the critical path issue.

I had to zip the programme (MS Project 2010) to upload it.

/Møller
Attached Files
File Type: zip 306, ARZ, Programme, 2016-04-12 -3.zip (521.0 KB, 11 views)
Reply With Quote
  #2  
Old 04-14-2016, 06:40 AM
JulieS JulieS is offline Need help understanding critical path and feedback on programme. Windows 7 64bit Need help understanding critical path and feedback on programme. Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I think the multiple critical paths makes the most sense. I'm guessing each road is a project unto itself and within the road, the work to complete that road is related. The only relationship between the road is resources. You've resolved the overallocations by leveling. Project does not take resources into account when displaying the critical path - only the task schedules.
Reply With Quote
  #3  
Old 04-15-2016, 01:42 AM
c991257 c991257 is offline Need help understanding critical path and feedback on programme. Windows 10 Need help understanding critical path and feedback on programme. Office 2016
Advanced Beginner
Need help understanding critical path and feedback on programme.
 
Join Date: Mar 2014
Location: Zambia
Posts: 61
c991257 is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
I think the multiple critical paths makes the most sense. I'm guessing each road is a project unto itself and within the road, the work to complete that road is related. The only relationship between the road is resources. You've resolved the overallocations by leveling. Project does not take resources into account when displaying the critical path - only the task schedules.
Thanks. I think your idea to consider each road as seperate project is good.

/Møller
Reply With Quote
  #4  
Old 04-15-2016, 06:18 AM
JulieS JulieS is offline Need help understanding critical path and feedback on programme. Windows 7 64bit Need help understanding critical path and feedback on programme. Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Critical Path workload forecasts Planner18 Project 1 07-01-2015 01:34 PM
Critical Path Length ketanco Project 5 03-15-2013 01:12 PM
Need help understanding critical path and feedback on programme. analysing contractor schedule for critical path ketanco Project 1 02-07-2013 06:49 AM
critical path starting in future ketanco Project 5 07-27-2012 02:50 PM
Need help understanding critical path and feedback on programme. Critical Path w/ 2 Calendars AndreT Project 6 07-27-2011 11:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:04 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft