#1
|
|||
|
|||
conflicting tasks with exception days
Hi, I have changed working times in a project to work weekends for a number of tasks but i want to not allow the weekend exceptions for other tasks within the same time frame but it wont allow me to so.
Any idea's please!!! |
#2
|
|||
|
|||
If you want to allow only certain tasks to work over the weekend, you'll need to make a separate calendar with the weekend work allowed and assign that calendar to the specific tasks. Changing the project calendar affects all tasks.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Newbie question : detection of conflicting tasks | Blitz | Visio | 1 | 03-03-2016 10:56 AM |
Changing color of a calendar exception | c991257 | Project | 1 | 01-19-2016 05:40 PM |
Exception days not accounted for in Gantt chart | Splint | Project | 1 | 09-02-2014 05:58 AM |
Database exception: login failed | rkoziol7 | Outlook | 0 | 05-23-2011 01:07 AM |
How to know if Meeting responses comes from serie or ocurrence/exception? | frilian | Outlook | 0 | 07-13-2010 12:04 AM |