Lenin Lenin is offline Earned Value Calculations - BCWP In Microsoft Project Windows 10 Earned Value Calculations - BCWP In Microsoft Project Office 2010 32bit
Novice
Earned Value Calculations - BCWP In Microsoft Project
 
Join Date: Mar 2016
Posts: 1
Lenin is on a distinguished road
Default Earned Value Calculations - BCWP In Microsoft Project

Hi I have a question regarding how Microsoft Project calculates BCWP. Let me ask the question in the form of an example

Scenario is based on single resource and single task with the EVM calculation using %complete (as opposed to physical % complete) with a contoured work profile.


Resource A costs £10/hr
Task 1 has a duration of 5 days with the following work profile (baseline work)

7.5h,3.75h,7.5h,3.75h,7.5h = 30hrs

Thus BCWS after day 5 is £300
£75,£112.5,£187.5,£225,£300

At the end of day 1 Resource A estimates that there is 3.5 days of work left (instead of 4) thus the new project duration is 4.5 days (as opposed to the base-lined 5). What is the BCWP?

I calculated (correctly) the %complete as 22% i.e. 1 day completed divided by the (new) duration 4.5 = 0.22 or 22%

So I thought perhaps BCWP 0.22 * £300 = £66.

This didn't look correct as the BCWS is £75 for day 1 and we managed to do more work that resulted in the estimate to complete reducing from 4 days to 3.5.

I then considered calculation from the point of view of base-lined remaining days and actual remaining days (I thought I read somewhere this is how it is calculated) i.e. 4 (base-lined) days left / 3.5 (new estimated) days left =1.143 * £75 = £85.714



According to my project this is correct against the resource. However Microsoft project reports £79.17 against the task. The BCWP against the tasks appears to drive the SPI.

My questions are
1. Is the method I used to calculate BCWP correct? i.e. remaining task duration method.
2. How does Microsoft Project arrive at £79.17 for the BCWP for the task when only 1 resource works on it and the BCWP against the resource is £85.714.

Any help greatly appreciated.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Earned Value Calculations - BCWP In Microsoft Project Microsoft Project Managing Planned / Earned Value & Actual Costs shane_dav71 Project 1 10-06-2014 06:07 PM
Earned Value Calculations - BCWP In Microsoft Project MS Project not calculating earned value correctly mtbtomo Project 1 10-23-2013 06:49 AM
Earned Value Calculations - BCWP In Microsoft Project Microsoft Word Form, DropDown Fields and Calculations Tracy Lynn Word VBA 2 09-29-2013 08:59 PM
Finding Earned Values for Different Baselines in a single project pratik6312 Project 1 08-22-2013 11:18 AM
Earned Value Calculations - BCWP In Microsoft Project Microsoft Word Calculations and Dropdown Fields Tracy Lynn Office 4 06-26-2013 07:36 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:29 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft