lcrevist lcrevist is offline Calculated Start Dates Based on Pre-scheduled Meetings Windows 7 64bit Calculated Start Dates Based on Pre-scheduled Meetings Office 2010 64bit
Novice
Calculated Start Dates Based on Pre-scheduled Meetings
 
Join Date: Mar 2016
Posts: 1
lcrevist is on a distinguished road
Default Calculated Start Dates Based on Pre-scheduled Meetings


I would like to create a task at the end of my project to review the results with the board. The board meetings are pre-scheduled and only occur once per month. For this reason, if the project slips and you miss a board meeting, you will not be able to make the presentation until the next scheduled board meeting.

I would like to know if there is a way to reference a table of the pre-scheduled board meetings and then set up a task to reference this table. See example below:

Evaluate Savings: Start 1/1/16 Finish 1/5/16
Develop Presentation: Start 1/6/16 Finish 1/9/16
Present to Board: If "Develop Presentation" is finished before 1/10/16, present to board on 1/10/16. If "Develop Presentation" is finished after 1/10/16, present to board in next meeting on 2/11/16.

Thanks!
Reply With Quote
  #2  
Old 03-12-2016, 10:32 AM
JulieS JulieS is offline Calculated Start Dates Based on Pre-scheduled Meetings Windows 7 64bit Calculated Start Dates Based on Pre-scheduled Meetings Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

My suggestion is to create a task calendar where the only working time is the Board meetings scheduled monthly. Assign that task calendar to the "Present to board" task. It will be scheduled only for the schedule you've set in the task calendar.

Do post back if you need further directions on either creating the task calendar or making the assignment of the task calendar to the task.
Reply With Quote
Reply

Tags
calculated dates, custom fields, table reference

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
difference between scheduled start and start ketanco Project 3 01-15-2015 07:53 AM
Calculated Start Dates Based on Pre-scheduled Meetings Excel to auto populate dates based on start and end patidallas22 Excel Programming 9 04-21-2014 03:14 PM
Calculated Start Dates Based on Pre-scheduled Meetings Difference between Manually Scheduled and Auto Scheduled tasks Mac265 Project 1 05-30-2013 05:25 AM
Calculated Start Dates Based on Pre-scheduled Meetings Add _ based on a calculated colums stovaaa Excel 4 03-09-2012 08:32 AM
Calculated Start Dates Based on Pre-scheduled Meetings Calculated dates. Ziggy-R Word 10 09-28-2010 01:42 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:33 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft