Old 02-21-2016, 11:11 AM
Jacke Jacke is offline New project Windows 7 64bit New project Office 2010 64bit
Novice
New project
 
Join Date: Feb 2016
Posts: 4
Jacke is on a distinguished road
Default New project

Hello everyone
I try use Microsoft project and I start check how it's works.
I make very simple project few tasks for one person, every time I have similar problem that. Resource/ worker have only planned one task in day even duration is 6hours and working day is 8. Otherwise resource have ex. 14 hours of work for day. Standrd day is from monday to friday from 7am to 3pm

For me the most important think is auto planning based on priority, duration time and deadline. Only if priority another task is bigger than deadline for task with lower priority should be moved
In the end I want make work plan for 5 people

1. It is possible to do in MProject ?


2. I inlcude in attachement example of file. Can somebody help me and make usefull schedulded from this file ?
Projekt2.mpp
Reply With Quote
  #2  
Old 02-23-2016, 01:34 PM
JulieS JulieS is offline New project Windows 7 64bit New project Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

With the exception of task 6 - your tasks are manually scheduled without duration, start or finish. You have a task calendar assigned to each task - versus setting up the project calendar to the correct schedule. Because your tasks have not schedule the 'worker' resource is not overallocated.

Change your tasks to autoschedule - remove the task calendar. Set the priority and level using priority, standard.
Reply With Quote
  #3  
Old 02-23-2016, 03:55 PM
Jacke Jacke is offline New project Windows 7 64bit New project Office 2010 64bit
Novice
New project
 
Join Date: Feb 2016
Posts: 4
Jacke is on a distinguished road
Default

Thank You for Your help its important for me.
Please look for picture, why working time is 361hours, if task is only 10 meeting with duration time 1hrs For me it schould be 10hrs
Capture.JPG

I try make new plan with autoscheduled and fill duration time but everthing is planned on one day. Ther isn't overload for worker1. Task 2 should start 22.02.16 13:00 and end in 23.02.16
scheduled2.mpp
Reply With Quote
  #4  
Old 02-25-2016, 09:25 AM
JulieS JulieS is offline New project Windows 7 64bit New project Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If there is a relationship between tasks (I can't start task 2 until task 1 is complete) then link them. I opened your schedule - it is apparently linked to another schedule which you didn't include.

The tasks are still all manually scheduled.

Regarding the above - all of the subtasks are manually scheduled. Do no assign the resource to the summary task - he/she should be assigned to each meeting.
Reply With Quote
  #5  
Old 02-25-2016, 11:44 AM
Jacke Jacke is offline New project Windows 7 64bit New project Office 2010 64bit
Novice
New project
 
Join Date: Feb 2016
Posts: 4
Jacke is on a distinguished road
Default

Thank You for information
Please look now I make auto scheduled, but everything start in the same time and worker is overload.
Capture2.JPG
It is possible to make schedule base on pririty and date before which should be done ? without connetion beetween tasks ?
scheduled3.mpp
Reply With Quote
  #6  
Old 02-25-2016, 12:05 PM
JulieS JulieS is offline New project Windows 7 64bit New project Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Have you leveled the resource? Do the tasks need to be linked?
Reply With Quote
  #7  
Old 02-25-2016, 12:13 PM
Jacke Jacke is offline New project Windows 7 64bit New project Office 2010 64bit
Novice
New project
 
Join Date: Feb 2016
Posts: 4
Jacke is on a distinguished road
Default

No tasks don't have to be linked (mayby sometimes) ( for planning small group of people it is very easy to use dead time and priority, task with higer priority should be planned first, to this time I make it manually in excel but now it is to big)

No I have not leveled resources, have I make it ? How I can make it
Reply With Quote
  #8  
Old 02-25-2016, 12:31 PM
JulieS JulieS is offline New project Windows 7 64bit New project Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Project will schedule autoscheduled task to start on the start date of the Project. If you need links - add them. If you have resources who are overallocated and want to use priority click Resources tab, set the leveling options, and then level the resources.

I also suggest taking a good course on Microsoft Project. It has a fair amount of complexity and getting someone who know the product well to walk you through the processes of building a schedule will save you hours of frustration.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
project server 2007 - project checkin failed at 37% marcoheras Project 1 07-01-2015 01:42 PM
Example for using Ms Project in construction project safaa Project 1 11-08-2012 05:54 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM
Different % complete in Project Center & View a Project mikaelbelchior Project 1 01-25-2006 12:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:57 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft