Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 01-10-2016, 04:08 AM
codeghi codeghi is offline Task filter for a resource view: is it possible? Windows 7 64bit Task filter for a resource view: is it possible? Office 2010 64bit
Advanced Beginner
Task filter for a resource view: is it possible?
 
Join Date: Jan 2010
Posts: 38
codeghi is on a distinguished road
Default Task filter for a resource view: is it possible?


Hello, I have a project plan based on resource pooling.
My project has many tasks and involves many resources: to view a specific range of information, I have added in "Gantt chart view" a new column (text1) with which I can filter a particular tasks.
I find very useful the "Team Planner view" and "Resource usage view" to track the resource job and I wonder if is it possible apply in these views the filter based on task.
If is not possible, could you suggest a workaround in order to visualize in resource view only a part of all the tasks?
Thank you so much.
Luca
Reply With Quote
  #2  
Old 01-10-2016, 06:25 PM
JulieS JulieS is offline Task filter for a resource view: is it possible? Windows 7 64bit Task filter for a resource view: is it possible? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The Resource Usage and Task Planner views are both resource usage views with assignment data. The data you enter into a custom field in the task view is not the same field on the resource side. For example: You add the Text1 field in the Gantt chart view and code tasks. If you then add the Text1 field to the Resource Usage view, you'll see it's blank.

You may be able to get what you want through VBA code to copy the information from a task field > assignment field - but you still won't be able to filter for just the assignment data.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Task filter for a resource view: is it possible? Resource Usage View - Is it possible to display resource names Andrea Schanz Project 6 09-22-2014 07:47 AM
Contact view filter not working gebobs Outlook 2 03-10-2014 06:28 AM
Task filter for a resource view: is it possible? filter 'Task name' shows all tasks Intruder Project 5 02-02-2014 07:29 AM
Task filter for a resource view: is it possible? Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Task filter for a resource view: is it possible? How to bring in one view task and resource fields? Evgeny Project 1 06-19-2013 06:55 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:51 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft