Hi,

I have to manage a number of projects and some tasks are common to more than one project.

i.e.



Project1 = task1, task2, task3

Project2 = task4, task1, task5

Project3 = task4, task5, task6

How can I share the tasks without duplicating them?

Kind Regards,

Michele
Reply With Quote
  #2  
Old 01-05-2016, 06:29 AM
JulieS JulieS is offline how to share task common to 2 projects? Windows 7 64bit how to share task common to 2 projects? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm not sure I follow completely. Are task 4 (for example) the exact same task - same dates, same resources? You can create dependencies (Finish to start, Start to Start, etc.) between tasks in different schedules - but you cannot have the same exact task appear in multiple projects.

Can you tell us a bit more about your scenario - we'll try to be more helpful.
Reply With Quote
Reply

Tags
common, link, task

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
how to share task common to 2 projects? Un-share and re-share a workbook? Officer_Bierschnitt Excel Programming 2 11-11-2015 06:59 AM
how to share task common to 2 projects? Common Document template for all projects ch1253 Office 1 11-15-2014 04:43 AM
how to share task common to 2 projects? Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
how to share task common to 2 projects? Need help with sorting a column by most common to least common mikenmike0001 Excel 5 12-06-2011 05:17 PM
how to share task common to 2 projects? Common mailbox analyzer/statistics NoStr0m0 Outlook 3 09-23-2011 05:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:03 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft