Hi,
You need to change the dependency to SS-3days; if you use fs-3 days you will get the start date as being 2 days earlier. because the day 1's will overlap. Hope this helps. Margaret |
#17
|
|||
|
|||
Oooohh you are so right Margaret, I should have thought about this!
Many many thanks again, you made my Friday! |
|