Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 12-04-2015, 07:49 AM
rowan.bradley rowan.bradley is offline Durations Windows 7 32bit Durations Office 2007
Novice
Durations
 
Join Date: Jan 2011
Posts: 11
rowan.bradley is on a distinguished road
Default Durations

When planning a project, in which field should I put the amount of work required for a task? In other words if building a wall takes 10 man-days, where do I put this 10?



I have so far been putting it in the Duration column, but every time I update the project, MSP modifies the Duration column to reflect the new duration of the project, including delays etc. This loses track of the original duration, so this can't be right.

What does Duration mean? The number of planned elapsed days (including holidays and non-working days, or not?), the number of planned man-days, the number of actual elapsed days so far, or the number of actual man-days so far, or what?

And when updating the project, where do I put the actual % complete of each task at this moment in time? I have so far been using the % Complete column (seems logical, right?) but I'm not sure this is right, because MSP is sometimes preventing me from updating this field.

Thanks - Rowan
Reply With Quote
  #2  
Old 12-15-2015, 05:34 PM
Guloluseus Guloluseus is offline Durations Windows 7 64bit Durations Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

There are 2 separate items here. Duration is the time a task will take to complete- if you have a duration of 10 days, and achieve 50% of the task after 10 days, you still have 50% (5 days) of duration left. When project updates from % complete, it looks at the duration -this can change depending on setings but is usually the most useful way to update.

When you put a task into project it uses the calender assigned to it (5 day working by default), so a 10 day task will span weekends (non working time) but the duration will still be 10 days, so no, holidays and weekends are not included, although they will affect the start/ finish dates.

The amount of work (or effort) is effectively ( in your example) the number of man daysinvolved in a task. If you have a task that requires 10 man days of work, and assign 1 man to it, then both the effort and duration will be 10. If you assign 2 men to it, the effort will stay at 10 (as it still takes 10 man days to complete) but the duration will reduce to 5 (2 men).
For a programme where resources are not assigned, the effort and duration will be the same (as it assumes only 1 unit assigned), but you can assign more units to a task, which will reduce the duration.

For updating, yes, % complete is usually correct. In my line of work (construction) tasks almost never take as long as programmed, due to 101 different factors, and % complete allows you to show actual progress in a meaningful way. While it may knock dates out of line, it lets you see the what and when and take appropriate action.
This often means that your finish day moves like a yoyo, but thats part and parcel of being a planner
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Durations Durations are not correct BarryB Project 1 04-27-2015 03:59 PM
Milestone durations fraserm Project 4 01-13-2012 08:43 AM
Adjusting All Durations by 10% skoz55 Project 1 01-13-2012 08:26 AM
Task and Summary Durations JR_12 Project 0 10-15-2011 05:07 PM
Calculate slide durations for song hb2010 PowerPoint 1 10-19-2010 06:41 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:31 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft