raminraiszadeh raminraiszadeh is offline Making Weekend a Working Day Windows 7 64bit Making Weekend a Working Day Office 2013
Novice
Making Weekend a Working Day
 
Join Date: Sep 2014
Posts: 22
raminraiszadeh is on a distinguished road
Default Making Weekend a Working Day

Hello,



I have created a calendar which includes the U.S. holidays. The project resources normally do not work on weekends, but they will need to work on one particular weekend (January 23 and 24 of 2015). How can I set these 2 days as working days?

Thanks!
Reply With Quote
  #2  
Old 12-02-2015, 03:05 PM
raminraiszadeh raminraiszadeh is offline Making Weekend a Working Day Windows 7 64bit Making Weekend a Working Day Office 2013
Novice
Making Weekend a Working Day
 
Join Date: Sep 2014
Posts: 22
raminraiszadeh is on a distinguished road
Default

Never mind... I found the solution!
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Making Weekend a Working Day Weekend Working Planner18 Project 1 10-29-2014 11:30 AM
Making Weekend a Working Day assign weekend 24 hr calendar to some tasks ketanco Project 1 05-12-2014 10:43 AM
Making Weekend a Working Day work during weekend outside normal calendar Intruder Project 13 02-27-2014 01:35 PM
Calculating Weekend Allowance WinIDS Excel 6 09-02-2011 01:27 AM
Code to auto-forward weekend messages Whang Outlook 0 06-16-2010 02:18 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:27 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft