Old 12-01-2015, 10:19 AM
Emanol Espina Emanol Espina is offline Seperate Cost per Resource Group and Taskname Windows 7 32bit Seperate Cost per Resource Group and Taskname Office 2013
Novice
Seperate Cost per Resource Group and Taskname
 
Join Date: Nov 2015
Posts: 4
Emanol Espina is on a distinguished road
Default

Hello Julie,

thank you very much for your answer.
I already created the filter as you said, but what I donīt understand is what you mean with step 3:

"3. Insert the Text 1 field and add the formula: [Outline Number] & " " & [Name]"

Cheers
Emanol
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Seperate Cost per Resource Group and Taskname [Project 2013] More accuracy with resource, unit %, and cost? cag8f Project 18 01-02-2016 01:51 PM
Seperate Cost per Resource Group and Taskname Different cost rates for resources for different projects linked to the Resource Pool Hanloujohn3515 Project 1 10-31-2015 11:58 AM
Seperate Cost per Resource Group and Taskname Cost resource not taken in real cost pascalbidouille Project 1 08-21-2015 01:25 PM
Portfolio Analyzer Cube - Cost Resource Question seanpears99 Project 2 03-07-2013 06:59 PM
entering values for a cost type resource ketanco Project 3 12-26-2011 09:25 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:48 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft