Hi,



I'm managing several project schedules all of which have the milestone task GoLive. In each project file I would like to capture the date for the GoLive task into a custom date column I've created. Is there a way to do this via a formula or other method?

Many thanks for your help.

Last edited by ebilbrough; 11-04-2015 at 12:20 PM. Reason: Clarity
Reply With Quote
  #2  
Old 11-04-2015, 12:51 PM
JulieS JulieS is offline Task Name / date in a formula or custom column Windows 7 64bit Task Name / date in a formula or custom column Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Usually you cannot extract data from a single task through a formula. Is the "GoLive" date a task finish or start date? Is it the finish date of the Project or does the project have tasks past "go Live"?

What do you want to do with that date? Custom columns normally have data for each task.
Reply With Quote
  #3  
Old 11-04-2015, 01:13 PM
ebilbrough ebilbrough is offline Task Name / date in a formula or custom column Windows 10 Task Name / date in a formula or custom column Office 2013
Novice
Task Name / date in a formula or custom column
 
Join Date: Nov 2015
Location: Austin, TX
Posts: 19
ebilbrough is on a distinguished road
Default

Thank you Julie for the reply.

The GoLive date is a milestone. There are tasks that occur after this milestone. Ultimately what I'm trying to achieve is having the GoLive task date appear in my SharePoint PWA Project Center view.

My SharePoint PWA view contains the Summary Level for each of my projects. I was hoping to capture this task date into a custom column which can be added to my view.

Let me know if that explains it better.

Many thanks.
Reply With Quote
  #4  
Old 11-04-2015, 01:17 PM
ebilbrough ebilbrough is offline Task Name / date in a formula or custom column Windows 10 Task Name / date in a formula or custom column Office 2013
Novice
Task Name / date in a formula or custom column
 
Join Date: Nov 2015
Location: Austin, TX
Posts: 19
ebilbrough is on a distinguished road
Default

Also, the GoLive milestone task does have a predecessor.
Reply With Quote
  #5  
Old 11-04-2015, 02:48 PM
JulieS JulieS is offline Task Name / date in a formula or custom column Windows 7 64bit Task Name / date in a formula or custom column Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

A custom field is going to show a value for each task. With a bit of fiddly work - you may be able to get it to work. For an example - set the Marked field for the "Go Live" date to "yes". Then in a date field:

IIf([Marked]=Yes,[Finish],ProjDateValue("NA"))

The formula should now show the date for the marked task.

Set the Calculation for group or summary rows to Maximum. Now that date appears at the Project summary task line.

Sorry - I can't suggest how to add the value to PWA. But yo should now have the DateX Project summary task value = Go live date.
Reply With Quote
  #6  
Old 11-05-2015, 10:27 AM
ebilbrough ebilbrough is offline Task Name / date in a formula or custom column Windows 10 Task Name / date in a formula or custom column Office 2013
Novice
Task Name / date in a formula or custom column
 
Join Date: Nov 2015
Location: Austin, TX
Posts: 19
ebilbrough is on a distinguished road
Default

That's exactly what I needed. Many thanks Julie!
Reply With Quote
  #7  
Old 11-05-2015, 12:59 PM
JulieS JulieS is offline Task Name / date in a formula or custom column Windows 7 64bit Task Name / date in a formula or custom column Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome and thanks for the feedback.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Task Name / date in a formula or custom column Embedded Excel in Powerpoint - custom animation, display column by column andytheanimal PowerPoint 2 01-20-2015 06:30 AM
Task Name / date in a formula or custom column MS Project to detect task level changes and record a date modified in custom field RJTMEYER Project 3 08-22-2014 07:38 AM
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
Task Name / date in a formula or custom column Automatically enter date into a column and make that column read only Mr Davo Excel 1 10-29-2012 01:07 AM
Task Name / date in a formula or custom column Custom field formula not working at summary task level abw1987 Project 3 10-05-2011 07:17 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:43 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft