A.S. A.S. is offline How to create "parallel" tasks? Windows 7 64bit How to create "parallel" tasks? Office 2007
Novice
How to create "parallel" tasks?
 
Join Date: Oct 2015
Posts: 3
A.S. is on a distinguished road
Default How to create "parallel" tasks?

Hello together,



have the following problem:

I have a Project plan that contains a base development section and several customer activity sections.

In the customer activity sections, I want to show a task that summarizes several base development tasks. Therefore, I want to start the summarizing task at "base development Milestone #1" and it should end with "base development Milestone #2". The Goal is that the summarizing task should change its duration automatically with the start/end Milestones accordingly.

I want to make an example, for better understanding: let's assume I want to develop a total new screw, let's call it the "67/18" screw". The Project starts with Milestone #1 and I have to do several things: find out the right material for that screw, prepare CAD models and drawings, let the sample shop produce some of those screws, make screwing Trials etc. ... finally, the Project Ends with Milestone #2.

In my customer section, I don't want to Show all that in Detail, I only want to Show one task, named "development of 67/18" screw", beginning with Milestone #1 and ending with Milestone #2. The Duration should Change automatically if the Milestone are shifted.

I tried to link the summary task with both Milestones, but it does not work without defining a Duration for that task. Does anybody have an idea?

FYI: I don't have ressources allocated to my Tasks.

Thank you and best regards,
Alex
Reply With Quote
  #2  
Old 10-26-2015, 09:56 AM
A.S. A.S. is offline How to create "parallel" tasks? Windows 7 64bit How to create "parallel" tasks? Office 2007
Novice
How to create "parallel" tasks?
 
Join Date: Oct 2015
Posts: 3
A.S. is on a distinguished road
Default

o.k. after some more search, I think a Hammock Task can help me ... but I don't like that solution very much: I don't see where the Task is linked to, and the solution seems to be sensitive to accidentially changes ... any further ideas how to solve that smarter?
Reply With Quote
  #3  
Old 10-27-2015, 04:48 AM
Guloluseus Guloluseus is offline How to create "parallel" tasks? Windows 7 64bit How to create "parallel" tasks? Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

I have had the same situation many times myself, usually where we need to see a summary of how long an area will be in use, and don't like hammocks much myself either.

depending on how you want to show things exactly, this may or may not solve it for you.
Creat a WBS (summary) called "Development of screw". Put 2 tasks in it, being milestone a and milestone b. Link milestone a to your milestone 1 (start of development) and b to 2 (end of development). The summary bar will then give you the overall duration of the required activities.

Its not particularly elegant, but it does show the required info. Because you are essentially copying the original milestones (the links from a to 1 and b to 2 mean the start/finish always remain the same) you have visibility of the actual dates while hiding the detail. I usually end up with a whole section of these (lots of areas of work) and its easiest just to stick them under a summary task again so you can see everything at once.

Hope that's useful to you.
Reply With Quote
  #4  
Old 10-28-2015, 02:29 AM
A.S. A.S. is offline How to create "parallel" tasks? Windows 7 64bit How to create "parallel" tasks? Office 2007
Novice
How to create "parallel" tasks?
 
Join Date: Oct 2015
Posts: 3
A.S. is on a distinguished road
Default

that's not exactly what I wanted to have, but it seems to be the easiest alternative (so easy that I wonder why I haven't figured that out myself) ... thank you !
Reply With Quote
  #5  
Old 10-29-2015, 03:06 PM
Guloluseus Guloluseus is offline How to create "parallel" tasks? Windows 7 64bit How to create "parallel" tasks? Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

Yeah.. I know its not an ideal solution, but it works
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Formula for filter "Incomplete Tasks for User..." patrickd123 Project 1 04-07-2015 08:15 AM
How to create "parallel" tasks? Need to create a "Yes/NO" Form and based on answers prompt for informatin jaradani Word 4 10-12-2014 09:42 PM
How to create "parallel" tasks? Create "Roll dice" simulation? (random number gen object?)) miiitchhh PowerPoint 1 10-14-2012 01:12 PM
Option "Autolink inserted or moved tasks" fargo71 Project 1 03-08-2012 10:27 AM
How to create "parallel" tasks? How to choose a "List" for certain "Heading" from "Modify" tool? Jamal NUMAN Word 2 07-03-2011 03:11 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:24 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft