Leveling Resources Help!
I have a project in MS Project 2013 that has many over allocated tasks. I do not have enough resources to finish the project by the due date. I need to figure out how many people to hire. Can Project automatically choose from group of resources/people who has the available time tor the task?
|
#2
|
|||
|
|||
No. Project cannot and will not automatically assign resources in any manner. You can use the Assign resources dialog and filter for resources who are available for X hours during a selected task duration.
|
Tags |
project 2013 |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
problem with leveling | r77 | Project | 5 | 09-17-2015 05:04 AM |
Certain Resources Not Leveling | PDX-ADM-TRM01 | Project | 1 | 04-27-2015 03:45 PM |
Question about leveling a project..... | sssb2000 | Project | 3 | 02-05-2015 12:11 PM |
Resources - only allow users to select from resources pool | grazi | Project | 1 | 04-04-2014 11:12 AM |
resource leveling in ms project | ketanco | Project | 1 | 12-24-2011 12:58 PM |