raminraiszadeh raminraiszadeh is offline Start date of successor task does not change Windows 7 64bit Start date of successor task does not change Office 2013
Novice
Start date of successor task does not change
 
Join Date: Sep 2014
Posts: 22
raminraiszadeh is on a distinguished road
Default Start date of successor task does not change


Using MS Project 2013. I noticed that increasing the duration of a task does not change the start date of the successor task if the successor task %completion is greater than zero. Why is this and is there a work-around?

Thanks
Reply With Quote
  #2  
Old 09-03-2015, 07:50 AM
JulieS JulieS is offline Start date of successor task does not change Windows 7 64bit Start date of successor task does not change Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

No it will not change because the successor task has an Actual Start date and Actual Start dates trump scheduled start dates. If a successor has been started, why would you want to change the start date later on?

However, if you have allowed splits in in-progress tasks (Options, Schedule) the successor task's remaining work should be scheduled based upon the original link relationship.
Reply With Quote
  #3  
Old 09-17-2015, 05:07 PM
raminraiszadeh raminraiszadeh is offline Start date of successor task does not change Windows 7 64bit Start date of successor task does not change Office 2013
Novice
Start date of successor task does not change
 
Join Date: Sep 2014
Posts: 22
raminraiszadeh is on a distinguished road
Default

Hi Julie,

Let's say I have 100 tasks which are all linked. If I increase the duration of task #1 by 5 days, I would like the Finish Date of task #100 to be pushed back by 5 days as well. However, if task #20 is 10% complete, it causes problems.

Regarding your second question, are you referring to the (Options, Schedule) option called "Split in-progress tasks"? If so, the option is checked.
Reply With Quote
  #4  
Old 09-19-2015, 01:41 PM
JulieS JulieS is offline Start date of successor task does not change Windows 7 64bit Start date of successor task does not change Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What are the links between your tasks Finish to Start? Start to Start? If everything is linked Finish to Start AND the tasks are autoscheduled AND you have split in progress selected even if task 20 has an actual start date (before its predecessor finished) and remaining part of the task should still be honoring the F to S link.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Project 2013 - Change GANTT Bar Colour By Main Task Date CaelanT Project 1 02-09-2015 12:50 PM
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
Start date of successor task does not change seeing successor information for a task ketanco Project 1 06-02-2012 09:35 AM
Task with Start date but no Due date? bplat Outlook 0 01-12-2012 08:10 AM
Start date of successor task does not change Task Start and End Dates OTPM Project 2 12-04-2011 09:14 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:18 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft