#1
|
|||
|
|||
Cost resource not taken in real cost
Hello,
In my planning I have defined one resource called HW which I have defined as as cost resource. I want to use this to log cost for some HW equipments. So on some task I assigned this HW resource and give it the value of my equipments. This price is correctly taken into the task cost. Problem is that when I fill my progress this HW value is never added into the task real cost and so even when I define my task as 100% done I still have a remaining cost on this task with this value. Have I done something wrong ? |
#2
|
|||
|
|||
You'll need to record the actual cost for the Hardware. Split your screen to show the task form - and when the task is 100% complete - enter the actual hardware costs in the task form formatted to show cost.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
[Project 2013] More accuracy with resource, unit %, and cost? | cag8f | Project | 18 | 01-02-2016 01:51 PM |
Cost Reporting 2013 | Steve. | Project | 7 | 05-14-2014 06:28 AM |
Portfolio Analyzer Cube - Cost Resource Question | seanpears99 | Project | 2 | 03-07-2013 06:59 PM |
How to rename cost column | ketanco | Project | 3 | 06-15-2012 03:06 PM |
entering values for a cost type resource | ketanco | Project | 3 | 12-26-2011 09:25 AM |