Hammock tasks
Once the hammock task is created, is there a way to display where is is linked to ?
|
#2
|
|||
|
|||
You can add the Edit Links command to a custom group on the ribbon. It will allow you to "Open source" and see where the links are coming from. Personally - I'd add a note when creating the paste link.
|
#3
|
|||
|
|||
Sorry I do not find that "Edit links" command.
My office version is in so maybe it has been translated differently ... Where do you usually find it ? |
#4
|
|||
|
|||
You'll need to customize your ribbon:
File > Options Customize Ribbon Add a new Group to an existing Ribbon or Create a new tab On the left under "Choose Commands from:" select All commands Scroll to find the "Edit Links" command in the list. Click Add to add it to your custom ribbon or group. |
#5
|
|||
|
|||
Sorry, my comment was not clear.
I know how to customize the ribbon. Just I do not have anything like "Edit links" in the command list even when I select "all commands" |
#6
|
|||
|
|||
Sorry - but it's listed under "E" in a US English installation of Project 2013. Not sure what language you are using. The icon looks like a piece of paper with a chain link in the lower portion.
|
#7
|
|||
|
|||
Ok I found it thanks to your icon description !
Bu the result is not so explicit. I see information like : Filename!LINK_161 So "filename" confirms its not a link from another file. Bu LINK_161 is not explicit as to where the link points to |
#8
|
|||
|
|||
You'll need to select the "Open source" button to have Project select the area providing the data. You can also double click on the linked area (start date) to have it select the start date it is getting the data from.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Hammock task issue | SaraJH | Project | 3 | 05-15-2014 05:52 AM |
Use VBA to create Hammock Tasks | seanpears99 | Project | 1 | 03-08-2013 08:58 AM |
updating not completed tasks or 0% tasks | ketanco | Project | 3 | 08-24-2012 05:59 AM |
Export Excel tasks into Outlook Tasks (2007 Version on both) | crazedmom | Excel | 0 | 12-29-2011 07:55 AM |
Why red tasks at last 3 tasks of 21 tasks | Jochen | Project | 2 | 04-13-2009 07:29 AM |