force task start on monday
Hello, Is it possible to force a task to start on monday ? I have task A and B B is successor to A. If A finishes friday => B starts monday What I 'd like is that if A finishes on tuesday, wednesday ... B will still start next monday. Any way to do this ? Thanks |
#2
|
|||
|
|||
As far as i know there is no innate way to do this, but there are workrounds. The first would be to manually check the task each time you update, and if its on the wrong day giver it a "start on or after" constraint.
Alternatively, you could set up a new calendar with just Mondays as working days, and put a new null milestone in (it can only occur) Link this from task A and to task B, so that it sits between them. This assumes task B is more than a day long- if its one day or less, you could just use the new calendar for ttask B itself. the problem this could create is that your critical path, if it runs through task B, would be lost.If its non critical no problem, but be aware that this could cause more problems. Hopefully someone has a beter solutin, but this is theone I would tend to use. |
#3
|
|||
|
|||
Just a quick point for clarity. The "buffer" task needs to have a duration >0 (it can be 1 min) in order to follow the Task Calendar schedule.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
'Monday to Friday' Date calculation help needed | ballst | Word | 10 | 12-16-2014 09:51 AM |
Team Planner-maintaining accuracy in task start and finish times | david_23 | Project | 9 | 04-19-2012 08:33 AM |
summary task calculating from project start | ketanco | Project | 1 | 01-02-2012 02:34 PM |
Task Start and End Dates | OTPM | Project | 2 | 12-04-2011 09:14 AM |
How to force the start of Style Paragraph to be small so that i don't get green under | Jamal NUMAN | Word | 1 | 07-11-2011 04:58 AM |