Hello,

Is it possible to force a task to start on monday ?


I have task A and B
B is successor to A.
If A finishes friday => B starts monday
What I 'd like is that if A finishes on tuesday, wednesday ... B will still start next monday.

Any way to do this ?

Thanks
Reply With Quote
  #2  
Old 06-27-2015, 10:01 AM
Guloluseus Guloluseus is offline force task start on monday Windows 7 64bit force task start on monday Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

As far as i know there is no innate way to do this, but there are workrounds. The first would be to manually check the task each time you update, and if its on the wrong day giver it a "start on or after" constraint.

Alternatively, you could set up a new calendar with just Mondays as working days, and put a new null milestone in (it can only occur) Link this from task A and to task B, so that it sits between them. This assumes task B is more than a day long- if its one day or less, you could just use the new calendar for ttask B itself.

the problem this could create is that your critical path, if it runs through task B, would be lost.If its non critical no problem, but be aware that this could cause more problems.

Hopefully someone has a beter solutin, but this is theone I would tend to use.
Reply With Quote
  #3  
Old 07-01-2015, 01:57 PM
JulieS JulieS is offline force task start on monday Windows 7 64bit force task start on monday Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Just a quick point for clarity. The "buffer" task needs to have a duration >0 (it can be 1 min) in order to follow the Task Calendar schedule.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
'Monday to Friday' Date calculation help needed ballst Word 10 12-16-2014 09:51 AM
force task start on monday Team Planner-maintaining accuracy in task start and finish times david_23 Project 9 04-19-2012 08:33 AM
force task start on monday summary task calculating from project start ketanco Project 1 01-02-2012 02:34 PM
force task start on monday Task Start and End Dates OTPM Project 2 12-04-2011 09:14 AM
force task start on monday How to force the start of Style Paragraph to be small so that i don't get green under Jamal NUMAN Word 1 07-11-2011 04:58 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:35 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft