Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 06-22-2015, 02:51 PM
cuseman03 cuseman03 is offline Please help clarify duration vs work in practical terms Windows 8 Please help clarify duration vs work in practical terms Office 2013
Novice
Please help clarify duration vs work in practical terms
 
Join Date: Jan 2015
Posts: 2
cuseman03 is on a distinguished road
Default Please help clarify duration vs work in practical terms

Hi,



I'm sure I'm like the millionth person to ask this question but I need some expert explaining here on how to effectively use both duration and work in Project. I understand duration to be a function of time, like calendar days. If one resource is working 100% on something then 1 day of 'duration' would be 8 hours. What happens though when you have a window of say 30 days to schedule a bunch of stakeholder meetings. You have 30 calendar days to get the job done but the job itself is super easy, maybe in total taking 2-3 hours of a resource's time. If I make duration 30 days, it thinks that task will take 240 hours. I have a lot of tasks in my current plan where the logic goes, as long as it is finished by this date or around this date. What is my best and simplest option to show this? I have 300 rows so at first I though maybe lag time, but that would be a real pain to do for a lot of rows?
Reply With Quote
  #2  
Old 06-23-2015, 08:09 AM
Guloluseus Guloluseus is offline Please help clarify duration vs work in practical terms Windows 7 64bit Please help clarify duration vs work in practical terms Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

This may or may not the solution you are looking for, but I will try anyway

Personally, I would put these into the programme with the correct duration- if its going to take a day, put it in as a day and resource appropriately. then link it to the preceding activity, so it has a start point, and a successor. If it needs to take place on a certain day (which from your question, it doesnt appear to) then you can use a "must start on or after" constraint. If necessary you can give it a "must finish on or before" constraint it is has to be done by a certain date, although a correct successor would also do that.
this will allow you to allow a correct duration and resourcing (and thus work) to the individual task (the meeting).

I would tend not to over allocate a duration, as this can give rise to more problems ifthe meeting drops back from its earliest point, and leads to other tasks being pushed out. As a rule of thumb I would almost always give a task a correct duration and resource to an activity as this gives a better reflection of its effect on other activities.
Reply With Quote
  #3  
Old 07-01-2015, 05:39 PM
JulieS JulieS is offline Please help clarify duration vs work in practical terms Windows 7 64bit Please help clarify duration vs work in practical terms Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're very close. Duration is the span between the start and finish dates of the task. The duration is always based upon the working calendar - so a 10 day duration task may span longer than 10 calendar days - assuming the project calendar has Saturday and Sunday as non-working days.

Work is the amount of effort expended by resources over the duration. It may be more than duration or less. For example: a one day duration task may have 24 hours of work if there are 3 resources assigned, each at 100%. Conversely, a week duration task may only have 10 hours of work if the resource is assigned at 25%.

One way of working with a scenario like yours is to enter the duration and set the task as Fixed Duration (Task Information - Advanced tab). Then assign the resource(s) and enter their work. I'd use the Task Form (split from a Gantt chart view) to be able to enter work for each resource you add.

To echo Guloluseus, if you allow a much longer duration, your resources will delay until the end of the duration. Better to set tighter durations and then use deadlines to monitor progress.
Reply With Quote
Reply

Tags
duration, work



Similar Threads
Thread Thread Starter Forum Replies Last Post
Please help clarify duration vs work in practical terms Work vs. Duration Cameronk Project 1 05-14-2015 02:29 PM
Please help clarify duration vs work in practical terms getting hung up on duration vs. work cuseman03 Project 5 05-14-2015 02:19 PM
Please help clarify duration vs work in practical terms overtime work effecting task duration user0044 Project 11 03-06-2012 07:20 AM
Work not changing duration benoldays Project 0 02-14-2011 08:21 PM
Duration changes fail to update work effort Panteledes Project 6 05-25-2010 02:27 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:53 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft