Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 07-17-2015, 02:10 AM
pascalbidouille pascalbidouille is offline EVM on summary tasks Windows 7 64bit EVM on summary tasks Office 2013
Novice
EVM on summary tasks
 
Join Date: Jun 2015
Posts: 18
pascalbidouille is on a distinguished road
Unhappy EVM on summary tasks


Hello,

I have some problem with the calculation of Earned value on summary tasks.
When I fill the %work done in a normal task : no problem EV is calculated, no problem.
But I have some resources that I have affected to a summary task.
In this case, I have the correct %work done calculated for my summary task based on sub tasks.
Bu EV for the summary task is calculated as SUM of EV from sub tasks and not as %work x Planned Value.
I thus get a Cost Variation between real cost and earned value.
Here is a screen shot of a small example :
(Sorry my MS Project version is in french so :
VA = EV
VC = CV
VP = PV
%travail = % work)

Reply With Quote
  #2  
Old 07-19-2015, 09:53 AM
JulieS JulieS is offline EVM on summary tasks Windows 7 64bit EVM on summary tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You should not assign resources to a summary task. The summary task's purpose is to summarize information from the subtasks. Take the resources off the summary tasks - save the baseline again.
Reply With Quote
  #3  
Old 07-21-2015, 02:18 AM
pascalbidouille pascalbidouille is offline EVM on summary tasks Windows 7 64bit EVM on summary tasks Office 2013
Novice
EVM on summary tasks
 
Join Date: Jun 2015
Posts: 18
pascalbidouille is on a distinguished road
Default

I was using summary tasks to log some travel costs.
While my "normal" tasks are used for my human resources work during weekday, my summary task allow me to log travel cost that are also calculated during week-ends.
This would mean i would have to create hammock tasks to log these travel costs but it is a hassle to assign resources to hammock tasks as for some reasons it sometimes ignore the link indicated in begin and end to calculate lenght of the task bases upon resource usage (even if I put these tasks as "capacity" type)
Reply With Quote
  #4  
Old 07-21-2015, 12:11 PM
JulieS JulieS is offline EVM on summary tasks Windows 7 64bit EVM on summary tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

As a suggestion, use Cost type resources for the travel costs. Their value is not counted in BCWP, BCWS, or ACWP. The values do count in BAC and EAC.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
EVM on summary tasks How do you create a Summary report of all 1N pages/tasks rduram OneNote 1 05-25-2015 04:22 AM
EVM on summary tasks Calculation of Percentage Completion of Summary Tasks raminraiszadeh Project 2 04-06-2015 06:38 AM
Automatic calculation of summary tasks Puddlerunna Project 1 10-15-2014 03:09 AM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
EVM on summary tasks Creating Report based on 'Task Summary' and 'Sub Tasks' alijahed Project 1 02-01-2013 04:20 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:39 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft