Old 06-15-2015, 12:51 PM
Lorrainewjh Lorrainewjh is offline how to set the task mode of recurring task Windows 7 64bit how to set the task mode of recurring task Office 2013
Novice
how to set the task mode of recurring task
 
Join Date: Jun 2015
Posts: 4
Lorrainewjh is on a distinguished road
Default how to set the task mode of recurring task

Hi I am new to project 2013. I met a problem when using recurring task function:

I have several tasks ongoing at the same time, one of them is spending 2 hours per day to check the data quality.


I set up a recurring task, select the start date, and set the end end point as 'after 20 occurance'.

I assume that the task should last for 20 working days, however, the summary of recurring task count the duration as 19.25 days.
I don't know how it is calculated. What's more, when I allocate myself to other tasks, it always shows that I am overallocated in
the recurring task.

I want the duration to be 20 days and I also want to allocate me to other tasks during the period. I thought maybe resetting the task mode of
the recurring task is a solution. Can anyone help me to fix the problem?

Any help would be appreciated! Thanks a lot!
Reply With Quote
  #2  
Old 07-01-2015, 05:44 PM
JulieS JulieS is offline how to set the task mode of recurring task Windows 7 64bit how to set the task mode of recurring task Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What is the duration of each occurrence? I'm guessing 2 hours. The duration is the span in working time from the start of the earliest occurrence to the end of the last. During that two hour period - I'm guessing you are assigned at 100%? If you assign yourself to any other task that overlaps the two hours, you are overallocated.

An alternative is to create a non-recurring task and set the duration to 20 days. Set the task as Fixed Duration - assign yourself and enter 40 hours of work. Project will assign you at 25% and schedule you for 2 hours per day. The 2 hours is spread throughout the entire day duration. You still have 75% available for other work on the same day.
Reply With Quote
Reply

Tags
project recurring task

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
how to set the task mode of recurring task Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
how to set the task mode of recurring task Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
How to task a event recurring in mutiple patterns? prabha_friend Outlook 0 02-01-2011 02:19 AM
filtering recurring task pascal Project 0 05-05-2010 08:07 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:23 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft