Old 06-15-2015, 12:51 PM
Lorrainewjh Lorrainewjh is offline how to set the task mode of recurring task Windows 7 64bit how to set the task mode of recurring task Office 2013
Novice
how to set the task mode of recurring task
 
Join Date: Jun 2015
Posts: 4
Lorrainewjh is on a distinguished road
Default how to set the task mode of recurring task

Hi I am new to project 2013. I met a problem when using recurring task function:



I have several tasks ongoing at the same time, one of them is spending 2 hours per day to check the data quality.
I set up a recurring task, select the start date, and set the end end point as 'after 20 occurance'.

I assume that the task should last for 20 working days, however, the summary of recurring task count the duration as 19.25 days.
I don't know how it is calculated. What's more, when I allocate myself to other tasks, it always shows that I am overallocated in
the recurring task.

I want the duration to be 20 days and I also want to allocate me to other tasks during the period. I thought maybe resetting the task mode of
the recurring task is a solution. Can anyone help me to fix the problem?

Any help would be appreciated! Thanks a lot!
Reply With Quote
  #2  
Old 07-01-2015, 05:44 PM
JulieS JulieS is offline how to set the task mode of recurring task Windows 7 64bit how to set the task mode of recurring task Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What is the duration of each occurrence? I'm guessing 2 hours. The duration is the span in working time from the start of the earliest occurrence to the end of the last. During that two hour period - I'm guessing you are assigned at 100%? If you assign yourself to any other task that overlaps the two hours, you are overallocated.

An alternative is to create a non-recurring task and set the duration to 20 days. Set the task as Fixed Duration - assign yourself and enter 40 hours of work. Project will assign you at 25% and schedule you for 2 hours per day. The 2 hours is spread throughout the entire day duration. You still have 75% available for other work on the same day.
Reply With Quote
Reply

Tags
project recurring task



Similar Threads
Thread Thread Starter Forum Replies Last Post
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
how to set the task mode of recurring task Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
how to set the task mode of recurring task Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
How to task a event recurring in mutiple patterns? prabha_friend Outlook 0 02-01-2011 02:19 AM
filtering recurring task pascal Project 0 05-05-2010 08:07 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:32 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft